Konecranes has secured two crane modernisation contracts from Brazilian renewable energy and electricity transmission company AXIA Energia to upgrade lifting equipment at the Manso and Mascarenhas de Moraes hydroelectric power plants.
Signed in May 2026, the projects are scheduled for
completion during 2027 and form part of AXIA Energia's broader programme to
modernise its hydroelectric generation assets.
The scope includes the electrical and mechanical modernisation
of five cranes, two overhead cranes and three gantry cranes, used for turbine
maintenance and plant upgrades.
Planned improvements include new drives and motors, braking
systems, variable frequency drives (VFDs), upgraded control and automation
systems, radio remote controls and refurbished operator cabins.
At the Mascarenhas de Moraes plant in Minas Gerais,
Konecranes will modernise a 200-ton gantry crane, while four cranes at the
Manso plant in Mato Grosso will also be upgraded by the end of 2027, enhancing
operational efficiency and supporting long-term hydropower reliability.
"Hydropower plant modernisations place high demands on
lifting equipment and its reliability. By upgrading the cranes' mechanical and
control systems, we are preparing the equipment for intensive use during the
turbine modernisation projects and improving its safety, reliability and
availability to support the plant upgrades," said Fellipi Pereira, Senior
Account Executive, Konecranes. -OGN/TradeArabia News Service