Saeed Mohammed Al Tayer
$50m Jebel Ali pipeline work on track: Dewa
DUBAI, February 25, 2018
Dubai Electricity and Water Authority (Dewa) has made significant progress on the supply, extension and commissioning of the major Dh185 million ($50 million) Jebel Ali-Al Hebab water pipeline, which extends across 30 km, said Dewa’s managing director and CEO.
“This supports our ambitious strategy and plans for the comprehensive development of electricity and water as per the Dubai Plan 2021, and meets the highest standards of availability, reliability and efficiency, to ensure customer demand. Dewa is working to improve the efficiency of its operations, and increase water flow to meet the growing demand for water in various parts of Dubai, to support the sustainable development of the emirate,” said Al Tayer.
The project also includes remote control and monitoring systems, which allow the continuous control of the main water transport network effectively, through remote-controlled valves in the control centre, which contribute to the isolation of faults in the shortest possible time, thereby reducing water losses in the network. This supports Dewa’s plans to upgrade its services to advanced levels and enhance its competitiveness in benchmarking, by achieving world-leading standards in reducing water losses compared to European and American utilities,” noted Al Tayer.
To date, 21.2 km, which is 69 per cent of the project, has been completed. The project includes the extension of 30 km of 1,200-mm-diameter glass reinforced epoxy (GRE) main water pipelines, to increase water flow along the Jebel Ali to Al Hebab road to meet increasing demand of water in Nakhali, Al Aweer, Al Qudra, and Dubai International Endurance City, in addition to projects along the Al Ain road.
The project is expected to be completed in May 2018, according to the planned programme,. – TradeArabia News Service