Genel completes 3rd well at Taq Taq in Iraq

BAGHDAD, December 25, 2016

Genel Energy, an independent oil and gas exploration and production company,   successfully drilled and completed the third and final well of the 2016 Taq Taq drilling programme in the main Shiranish reservoir.

The well is naturally flowing at c.8,000 bopd.

Gross Taq Taq production is currently c.40,000 bopd, with Q4 2016 averaging 45,000 barrels of oil per day (bopd) to date. The Pilaspi reservoir is being readied for production in January 2017, and is expected to contribute c.3,000 bopd.

The three Shiranish wells (TT-27x, TT-07z, and TT-16y) drilled in the 2016 campaign are currently producing a combined c.9,000 bopd. Discussions are ongoing between the Taq Taq partners over a potential workover of TT-07z. This well flowed on test at 5,000-9,000 bopd, although as a result of mechanical issues experienced during well completion activities TT-07z has recently been producing at 400 bopd.

Genel’s net working interest production from the Taq Taq and Tawke fields has averaged 53,500 bopd in 2016 to date.

The updated Field Development Plan and the Competent Person’s Report for Taq Taq are on track for completion in Q1 2017.

Genel plans to issue a trading and operations update in respect of 2016 financial and operating performance and 2017 outlook on January 24. – TradeArabia News Service