Wednesday 6 November 2024
 
»
 
»
ON TRACK

UAE sees $10bn gas project ready by 2014

Abu Dhabi, October 16, 2012

Abu Dhabi's huge sour gas development is on track for completion in late 2014 despite the challenges $10 billion project faces, the CEO of the operating company said on Tuesday.

"Our facilities are 60 per cent complete and the drilling is 20 per cent complete. By late 2014, we will be delivering the project," Saif al Ghafli, CEO of Abu Dhabi Gas Development Company told an energy conference.

The risks associated with drilling, the size of the facility, the environmental and technical issues are some of the challenges that have to be overcome, he said.

The $10 billion project will deliver 500 million cubic feet per day of clean gas as well as condensates, natural gas liquids and sulphur once completed, he added.

Al Ghafli said the costs have been according to the plan. US-based Occidental Petroleum was awarded the Shah Gas project early in 2011.-Reuters




Tags: UAE | abu dhabi | Drilling | Shah gas project |

More Energy, Oil & Gas Stories

calendarCalendar of Events

Ads