Monday 23 December 2024
 
»
 
»
Story

Work has already started on the cladding of the dome.

Louvre Abu Dhabi in new dome installation milestone

ABU DHABI, October 22, 2014

Abu Dhabi's Tourism Development & Investment Company (TDIC) has announced the full installation of the 7,000-tonne Louvre Abu Dhabi dome structure, which consists of 85 super-sized steel elements.

The work on the last of those 85 pieces has finished, completing today the dome’s complex puzzle-shaped structure. The first super-sized element was lifted and put into place in December last year.

Now the dome sits atop 120 temporary support towers, which will be later on disassembled and removed leaving the dome, as initially designed, resting on four main piers only, said TDIC, a master developer of major tourism, cultural and residential destinations in Abu Dhabi.

Work has already started on the cladding of the dome, whereby a total of eight layers of aluminium and stainless steel inserts, will be placed in a clockwise direction, above and below the steel frame, it stated.

To achieve the ‘rain of light’ effect within the museum, these cladding pieces have been carefully engineered in specific sizes and orientations forming approximately 8,000 stars in both the upper and lower layers, according to TDIC.

"These star-shaped pieces range from 3.5 to 13.5 m wide depending on their position and location within the cladding design," said its CEO Ali Al Hammadi.

"We are very pleased that Louvre Abu Dhabi’s dome structure installation has now been completed and that the work is progressing as planned. This is a major milestone in the museum’s development, and a great achievement for everyone involved because the execution of the design is very complex and one that is unprecedented in the architectural world," he stated.

Elsewhere, great strides have been achieved across Louvre Abu Dhabi’s construction site, he added.

According to TDIC, a total of 144,000 cu m out of 145,000 cu m of concrete has been poured till date. Furthermore, a total of 33,000 tonnes of reinforcement steel has been used and more than 18,500,000 man hours completed on site.

The construction of all the galleries has been completed structurally, along with the concrete work for the museum’s basement levels as well as the security screening facility and a highly secure 7-m-deep basement through which authorised vehicles will transport all the artwork of the museum.

Moreover, work is progressing on the 1.2-km Saadiyat Tunnel which will be the main entryway for the artworks as they are transported to their destination, said the TDIC in a statement.

Mock-up galleries of Louvre Abu Dhabi, which have been constructed for finalisation and sign-off, sit a few metres off site. This mock-up building is by and large a testing ground to verify, evaluate and, ultimately, seek approvals for the architectural quality and aesthetics of works for the museum - both internally and externally.

Jassim Al Hammadi, the director of infrastructure at TDIC, said: "The dome is the museum’s most prominent feature and has been by far the most challenging element to construct on site. However, we are working round-the-clock to meet our deadlines and make sure that the project is delivered on schedule."

"We will soon start the marine excavation process, which will see the revetment, or breakwater area, surrounding the museum’s temporary platform removed in a strategic process. As work progresses, flooding will start to take place, resulting in Louvre Abu Dhabi’s final floating appearance," noted Al Hammadi.  

Designed by Pritzker-prize winning architect Jean Nouvel, Louvre Abu Dhabi will encompass 9,200 sq m of art galleries.

The 6,681-sq-m Permanent Gallery will house the museum's permanent collection taking the visitor through a universal journey from the most ancient to contemporary through art works from different civilisations. The Temporary Gallery will be a dedicated space of 2,364 sq m presenting temporary exhibitions of international standards.  

Louvre Abu Dhabi, when completed, will be one of the premier cultural institutions located in the heart of the Saadiyat Cultural District. These feature Zayed National Museum and Guggenheim Abu Dhabi - both also designed by world-renowned Pritzker-prize winning architects.-TradeArabia News Service




Tags: abu dhabi | installation | Louvre | Dome |

More Construction & Real Estate Stories

calendarCalendar of Events

Ads