Dubai Lagoon construction on track

Dubai, June 23, 2010

The construction of Dubai Lagoon, a residential apartment community, is on track to meet the delivery deadlines, starting with Zone 1, which is due for completion by the end of 2010, said its developer.

Schön Properties, a leading regional property developer, also revealed that it is currently in the process of short listing leading companies to be invited to bid on the infrastructure works, MEP and other finishing works for the project.

Expected to be delivered the earliest, Zone 1 is the closest to completion, said main contractor Bin Sabt. It is expecting to finish building C+10 first, to be followed by C9, H11, and C12 by November, it said.

The second batch, which will include buildings C7, C8, C13, and C14 are targeted for delivery by year-end.

On Zone 3, main contractor Belhasa is set to commence works on buildings A19 and A23, with plans to construct three to four slabs per month on the entire zone.

With a view to complete the full structure within the next 12 months, and the MEP works and finishing six to seven months thereafter, the contractor is confident that the zone will be ready for delivery by the end of 2011, a statement said.

“The strong sense of cooperation among all our contractors and suppliers plays a pivotal role in the impressive speed by which this monumental project is being built, which will enable us to deliver the initial phases on schedule,” said Danial H Schön, vice president, Schön Properties.

With backfilling for Zone 2 already completed and the pouring of the concrete blinding almost finished, the appointed waterproofing contractor BMC is gearing up to complete the waterproofing under the raft foundation within the next two weeks.

Main contractor Commodore Contracting further announced that the raft foundation steel works has already started, with the double basements to be completed in four months and the ground floor slab to be cast within the next five to six months.

The building permit for Zone 4 has already been transferred and backfilling is nearing completion, while Commodore Contracting is gearing up to commence works on Zone 4 as per the schedule set for Zone 2, with a one-month lag, the statement said.

“We want to commend the excellent work of our partners, especially the main contractors, who are fuelling our continuous efforts to ensure the prompt completion of Dubai Lagoon,” said Asher H Schön, vice president, Schön Properties.

“We would also like to acknowledge the contributions of our project consultant Mazaya in achieving these encouraging developments,” he concluded. – TradeArabia News Service




Tags: Dubai Lagoon | Schon Properties | Belhasa | Residential apartment | Zone 1 | Commodore |