Italian energy company Eni has announced the commissioning of a 120-megawatt (MW) gas power plant in Kazakhstan’s Mangystau Region, marking a milestone in the development of the country’s first large-scale hybrid power generation project.

The facility forms part of the 247 MW Mangystau Hybrid Power Plant Project, developed in partnership with Kazakhstan’s national oil and gas company KazMunayGas and Plenitude, a company jointly controlled by Eni and Ares.

Completed after 12 months of construction, the project integrates solar and gas power generation, with wind energy scheduled to be added in a later phase. It aims to provide reliable and lower-carbon electricity to KazMunayGas subsidiaries in the region while supporting the modernisation and diversification of Kazakhstan’s energy system.

The construction and commissioning of the gas facility involved approximately three million man-hours without a Lost Time Injury (LTI), reflecting the project's safety performance and coordination among local stakeholders, Eni said.

The project is progressing in phases. Its 50 MW solar power plant was commissioned in September 2025, while the gas facility reached First Industrial Electricity in July 2026 before completing commissioning.

The next phase involves constructing a 77 MW wind power plant. Most civil engineering works are expected to be completed by the end of 2026, allowing installation of the first wind turbine generators. Commercial operations are scheduled to begin in 2027, completing the hybrid facility's planned 247 MW capacity.

The development builds on the longstanding partnership between Eni and KazMunayGas and supports efforts to strengthen electricity infrastructure and advance Kazakhstan’s energy transition objectives.

Eni has maintained a presence in Kazakhstan since 1992, with interests in several major oil and gas projects. It is a co-operator of the Karachaganak field, holding a 29.25 per cent interest, and owns a 16.81 per cent stake in the North Caspian Production Sharing Agreement consortium. The company also holds interests in the Caspian Pipeline Consortium and the Baku-Tbilisi-Ceyhan pipeline.

Through its subsidiary Plenitude, Eni has also expanded its renewable energy portfolio in Kazakhstan. Its existing assets include 96 MW of wind capacity at the Badamsha Wind Farms in the Aktobe Region and a 50 MW solar power plant in Shaulder, Turkestan Region.

The Mangystau project further expands the company's involvement in the country's energy sector, combining conventional and renewable generation to support more diversified electricity supplies. -OGN/TradeArabia News Service