Energy, Oil & Gas

Nama invests $58.44m in Muscat electricity network projects

MUSCAT
Nama invests $58.44m in Muscat electricity network projects

Nama Electricity Distribution Company is investing RO 22.47 million ($58.44 million) in electricity infrastructure projects across Muscat Governorate under its 2026 investment plan, as it seeks to strengthen grid capacity, improve reliability and meet rising demand driven by population growth and urban expansion.

The investment programme covers the development of medium- and low-voltage networks, the construction of new substations and the reinforcement of existing electricity infrastructure across the governorate’s wilayats.

Mohammed Al Qari, General Manager of Major Projects at Nama Electricity Distribution Company, told Oman News Agency (ONA) that the projects form part of the company’s broader efforts to enhance the efficiency of electricity distribution networks and improve service quality for subscribers.

He said the investments are designed to accommodate increasing electricity consumption while supporting Muscat’s urban, economic and developmental expansion.

Of the total planned investment, RO 12.78 million has been allocated to medium-voltage (33 kV) network projects, while RO 7.63 million will fund new electrical networks at 11/0.415 kV. A further RO 2.06 million has been earmarked for reinforcing existing networks at the same voltage levels.

Actual investment expenditure between January and August 2026 reached RO 10.791 million. This included RO 6.4 million for 33 kV network projects, RO 4.06 million for establishing new networks and RO 331,000 for grid reinforcement works.

Major projects completed

The company has completed executive works on several key electricity infrastructure projects, including the construction of primary substations in Sultan Haitham City at a cost of approximately RO 5.27 million.

Other completed projects include the upgrading of Qurum substation, costing around RO 2.133 million, and the upgrading of Al Hail North substation in the Wilayat of A’Seeb, at a cost of RO 993,000.

The construction of Wadi Ruwi substation, with a capacity of 2×20 MVA, has also been completed at an estimated cost of RO 1.228 million.

Several additional projects have reached 100 per cent completion and entered the closure phase. These include the Rusayl Industrial 1 substation, with a capacity of 2×20 MVA, costing approximately RO 1.293 million.

The completed works also include the replacement of electrical assets at Azaiba South substation at a cost of RO 593,000, as well as improvements at Muttrah stores. The latter project involved constructing a new building, replacing 33 kV switchgear equipment and installing a ring main unit, at a total cost of around RO 788,000.

Meanwhile, a grid reliability enhancement project involving the addition of a new 33 kV electrical feeder in A’Seeb was completed at a cost of RO 155,000.

Al Qari also confirmed the completion of primary and secondary utility network works for the first phase of Sultan Haitham City by September 2026. The project, valued at approximately RO 2.792 million, provides essential electricity infrastructure to support the development of the new city.

Projects under implementation

Work is continuing on several major projects across Muscat Governorate, with construction progressing at different stages.

In A’Seeb, the Misfah substation project, with a capacity of 3×20 MVA and an estimated cost of RO 2.396 million, had achieved 51.21 per cent completion by September 2026.

In Qurayyat, construction of a new substation with a capacity of 2×20 MVA, valued at RO 1.377 million, had reached 56.3 per cent completion.

The Al Ansab Heights substation project in Bawshar, costing approximately RO 2.078 million, recorded 85.4 per cent completion, while the Yiti substation upgrade in Muscat had reached 5 per cent completion. The latter project carries an estimated cost of RO 1.747 million.

In addition, the supply of 11 kV electrical capacitor banks for several primary substations across Muscat has reached the testing and commissioning stage, with 95 per cent completion. The project, valued at RO 593,000, is intended to improve grid performance and operational efficiency.

Pipeline of future investments

Nama is also progressing with the preparatory and design stages of several future projects aimed at further expanding the governorate’s electricity infrastructure.

These include the proposed Al Shabri substation in A’Seeb, estimated to cost RO 2.193 million, and Al Maabilah South substation, with an allocated cost of RO 2.501 million.

Plans also include constructing a new substation in Bawshar with a capacity of 2×20 MVA, at an estimated cost of RO 2.32 million, alongside replacing transformers at Al Falaj substation in Ruwi, a project valued at approximately RO 450,000.

Al Qari said the company remains committed to delivering its investment projects according to approved schedules while maintaining the highest standards of quality and operational safety.

He added that the ongoing and planned developments will strengthen the electricity network’s capacity to accommodate future demand, improve service reliability and support sustainable urban and economic growth across Muscat Governorate.