Friday 22 November 2024
 
»
 
»
Story

IOEC set for drilling ops at South Pars Phase 14

TEHRAN, June 14, 2016

Iranian Offshore Engineering and Construction Company (IOEC) will commence offshore drilling operations at Phase 14 of t South Pars Gas Field by mid-July, said Iran Daily, quoting a top official.

Physical activities at the phase will begin once the first drilling rig is installed within a month, Farzad Ghazali, operator of the phase, was quoted in the report, which cited Shana.

A total of 22 wells are planned in the phase and drilling operations will take two and a half years to complete, he said.

Around $762.5 million has been invested in drilling the wells, he added.




Tags: South Pars | IOEC | Offshore drilling |

More Energy, Oil & Gas Stories

calendarCalendar of Events

Ads