Jacket installation ..... calls for highly specialised engineering
by McDermott.
McDermott wins Qatar Petroleum contract
DOHA, March 4, 2015
McDermott International, a leading provider of integrated engineering, procurement, construction and installation (EPCI) services, said it has been awarded a large project for a new jacket, temporary deck and replacement umbilical by Qatar Petroleum for the North Field Alpha gas development, offshore Qatar.
The work is expected to be executed through the second quarter of 2016 and will be included in McDermott’s first quarter 2015 backlog, said the company in a statement.
The brownfield contract includes front-end engineering design verification, detailed EPCI and commissioning of a new six-legged, 15-slot wellhead jacket and temporary drill deck, with a total weight of approximately 5,000 tons.
The work also includes the decommissioning, removal, replacement and pre-commissioning of 2.6 miles of composite umbilical and a fiber optic cable, in the Maydan Mahzam field.
Commenting on the win, Tom Mackie, the vice president, Middle East, said: "For more than 30 years, McDermott has successfully delivered numerous projects for Qatar Petroleum and its partners in Qatar’s North Field, and we are pleased to further build on this relationship, as they focus on enhancing their oil recovery and production capability."
Detailed engineering, procurement and construction is expected to be carried out by McDermott’s specialist teams in Dubai, UAE, with vessels from the McDermott global fleet scheduled to undertake the installation work in 2016.
“We believe our ability to provide a fully integrated EPCI solution from one centralised location in Dubai will enable us to be more effective at ensuring certainty of delivery across all stages of the project allowing for more scheduling flexibility, and higher quality and safety, which is critical when working within an actively producing field, to ensure minimal operational interruption,” he added.-TradeArabia News Service