Thursday 18 April 2024
 
»
 
»
LARGEST PETCHEM FACILITY

Al-Labban ... commissioning in March

Sadara plans to start up mixed-feed cracker in March

AL KHOBAR, January 28, 2016

Sadara Chemical, a $20 billion petrochemical joint venture between Saudi Aramco and Dow Chemical, plans to start up its mixed-feed cracker in March, its chief executive Ziad Al-Labban said.
 
"The Sadara mixed-feed cracker is scheduled to be commissioned in March and will ramp up to a feed of 85 million standard cubic feet per day of ethane and 50,000 barrels per day of naphtha," Labban told Reuters.
 
The Sadara complex is the largest petrochemical facility to be built in a single phase and comprises 26 integrated facilities. All facilities are scheduled to be commissioned by the end of 2017. The complex is located in Jubail, on the Gulf coast of the world's largest oil exporter.
 
In December, Sadara said it had started producing its first products. Labban said the first production of solution polyethylene was shipped to China. 
 



Tags: Saudi Arabia | sadara | chemcial |

More Industry, Logistics & Shipping Stories

calendarCalendar of Events

Ads